The project was originally designed as a one directional 47cm ribs and insitu-cast beams.
After the contractor's value engineering on the structural systems, a redesign of the three buildings was done using hollow core and post-tension two ways slabs and beams, making the construction faster, cheaper and durable.
Main Contractor: Man Enterprise
Consultant: Khatib & Alami
Location: Ras beirut
Project Size: 15000 m²
Date Completed: 2012-02-29