Installation Process

01
Installation Process
Contract is Signed
Both parties signing the document agree to the terms in it and their contractual duties and obligations.
02 1 Week Period
Installation Process
Drawings Developement
Our office employees are dedicated to satisfying all of our customers needs. Detail drawings show a small part of the house at a larger scale, to show how the component parts fit together. They are also used to show small surface details, for example electrical elements.
03 1 to 8 Weeks Period
Installation Process
Construction permit starts
The homeowner will receive one of the submitted construction drawing sets back with proper signatures from the municipality added to the cover sheet. This is the 'insurance' that the project will be built legally and safely.
04 2 Weeks Period
Installation Process
Excavation
Before any foundations can be installed or casted, the soil under the house location and its proximity has to be leveled, allowing for the foundations to sit properly.The road leading up to the house should be large enough to accommodate a flat bed 12 meter trailer; any sharp turns near the site should be enlarged beforehand by the client.
05 1 Week Period
Installation Process
Foundations
After the contract has been signed, a soil investigation is undertaken by the client to acquire the soil capacity. If rocky terrain or good soil nature and capacity are found then the Mega Box does not need any additional foundation than what we provide, it only requires a leveled ground. If not, strip foundations under the Mega box have to be cast. In the mean time, Mega Prefab manufactures the concrete boxes.
06 1 Week Period
Installation Process
Concrete Modules Installation
The prefabricated modules are then transported on site already equipped with the kitchen, bathrooms and most of the finishing, keeping only minor tasks to be done on site.Up to four boxes (app 100m2) are installed per day with one crane and a crew of four workers.
07 8 Weeks Period
Installation Process
Finishing
Up to eight weeks of finishing touches and connections remain to be done on site such as roof waterproofing, roof tiles installation, joint treatments between boxes and mechanical connections to outside the house.Once ready, we will hand over the house to the owners, a snag list of all installed systems will be checked in the presence of the client.
  • 01
  • 021 Week Period
  • 03
  • 042 Weeks Period
  • 051 Week Period
  • 061 Week Period
  • 078 Weeks Period
01
Installation Process
Contract is Signed
Both parties signing the document agree to the terms in it and their contractual duties and obligations.